Below you will find our standard lead times for all our user interfaces products. You will also find our standard lead times for manufacturing pre-production engineering, product samples, and production parts.
SMART user interface projects typically require 40 to 60 working days for the design and development phase. Actual timelines depend on the complexity of the electrical, firmware, and system requirements.
Standard sample lead time for SMART user interfaces is 30 working days after the design and development phase has been completed.
Production parts for SMART user interfaces typically require 30 to 40 working days. Lead times can vary based on production quantity and material availability.
Membrane switches and silicone rubber keypads generally require 3 to 5 working days for pre-production engineering, followed by 25 working days for samples and 25 working days for production parts. Graphic overlays typically require 2 to 4 working days for pre-production engineering, with 25 working days for both samples and production production orders.
Yes. Lead times may vary depending on factors such as design complexity, electrical and firmware requirements, order quantity, material lead times, and any specialized manufacturing or testing requirements associated with the project.
From samples to production, we will ensure your HMI project moves through manufacturing based on the lead times you need. Don't miss your project deadline, act now!